Ginigera-Raichur New Railway Line Updates:
CRS Inspection of Gangavathi - Karatagi section (28km) successfully completed on 30/05/2020
CRS Inspection of Gangavathi - Karatagi section (28km) successfully completed on 30/05/2020
2 Posts
Ground leveling and bridge works going on between Karatagi & Sindhanuru..may complete by Sep 2021.
Pls share are there any works going on in Sindhanur - Manvi Section or in Raichur - Manvi Section ?