Blog Entry# 4762735
Posted: Oct 30 2020 (18:26)
12 Responses
Last Response: Nov 19 2020 (22:57)
12 Responses
Last Response: Nov 19 2020 (22:57)
CRS for electrified line likely to be happen on 15th November for Manigram-Farakka section.
#Electrification
#Electrification
7 Posts
Pending section for doubling in Azimganj - Farakka path:
1. Jangipur to Sujipara: New railway bridge over Ahiran feeder canal is going on for doubling
2. Dhuliyan to Farakka: Few small railway bridges are in construction phase.
...
more...
1. Jangipur to Sujipara: New railway bridge over Ahiran feeder canal is going on for doubling
2. Dhuliyan to Farakka: Few small railway bridges are in construction phase.
...
more...
I mentioned the status yesterday in the same post here /blog/post/4762735
First e loco trial will be done then only the officials of core nod the approval of crs we can expect that in early dec