Dhasha jetalsar #gc update
95% Earthwork, 90% blanketing completed. All Bridges completed. 45 out of 48 RUBs completed. S&T Rooms at all 10 Stations have been completed. Track linking of 65 Kms. completed, work is in progress. Commissioning target, December 2021, Availability of adequate funds work is in progress