Detailed construction progress Update for PF4 and PF5 at Muzaffarpur Jn.
As evident from the pics, almost 50% of civil work is done. Central FOB has been connected to the new platform, and other FOB is left out. A third new FOB is under construction as well, whose pillars have been laid down.
The remaining civil work is for PF shed construction. After that, passenger amenities such as benches, taps, lighting, fans, PA system will be installed.
Hopefully...
more...
As evident from the pics, almost 50% of civil work is done. Central FOB has been connected to the new platform, and other FOB is left out. A third new FOB is under construction as well, whose pillars have been laid down.
The remaining civil work is for PF shed construction. After that, passenger amenities such as benches, taps, lighting, fans, PA system will be installed.
Hopefully...
more...
2 Public Posts - Fri Oct 08, 2021
4 Public Posts - Sat Oct 09, 2021
They have another excuse already. MFP has severe Pitlines constraints, hence Sonpur Division is originating new trains from Barauni. Don't expect any ECR based train from MFP, although trains with Platform turn-around still might be possible.
3 Public Posts - Sat Oct 09, 2021