"The main work Tarakeshwar – Bishnupur (82.47 Km) – New line - Work was sanctioned in 2000-01 and cost of the project is Rs 480.68 Cr. Tarkeshwar –Goghat (33.94 km) New line – Commissioned on 06.03.2016 Mayonapur – Bishnupur (22.68 km) New line – Commissioned on 16.09.2012 Section Goghat – Kamarpukur (5.50 km) was completed during 2018-19 except 950m stretch where the work is stopped by local villagers at Bhabadighi pond for last 4-5 years. State Govt. is pursued repeatedly. Balance section (a) Kamarpukur – Jairambati (3.30 KM) falling in Hoogly District. Land in 0.755 Km handed over to Rly and balance 2.545 Km land acquisition done but compensation has not been distributed. Balance in 17.05 Km entire land is handed over to Railway. (b) Mayonapur – Jairambati (excl) falling Bankura district and Land Acquisition has been completed recently and handed over to Rly. Now Tender for the section Mayonapur –...
more...
more...
1 Public Posts - Sun Apr 10, 2022
Tender for Maynapur Kamarpukur including Goghat yard is released for bidding. Complete land of the entire section has been provided to Railway. Bhabadighi stretch is being re-examined to acquire land in north of the lake in order to shorten length and avoid the water body.
₹189 Cr for Maynapur Kamarpukur
₹31 Cr for Kamarpukur Goghat new alignment and earthwork wherever necessary.
Existing acquired...
more...
₹189 Cr for Maynapur Kamarpukur
₹31 Cr for Kamarpukur Goghat new alignment and earthwork wherever necessary.
Existing acquired...