Electrification updates of SRR-CLT Strekch:--
As of now, Overhead work is completed till Kallayi station @ Calicut.
Wiring is completed till almost Meenchantha, and 99% upto Feroke
As of now, Overhead work is completed till Kallayi station @ Calicut.
Wiring is completed till almost Meenchantha, and 99% upto Feroke
28 Posts
As of now, only leakout news of 3 trains;
They are
1. KCVL-Jaipur (via CBE) - proposed by NWR, but it should be via Konkan, i suggest
2. KCVL-SRC (via Erode) - proposed by ER. Need of the hour
3....
more...
They are
1. KCVL-Jaipur (via CBE) - proposed by NWR, but it should be via Konkan, i suggest
2. KCVL-SRC (via Erode) - proposed by ER. Need of the hour
3....
more...
Poles have been laid from Valapattanam to Kasaragod and foundation work has reached Netravati Bridge outside Mangalore. Hope the recent accidental death of 2 workers doesn't effect the pace of the work being carried out.
New materials unloaded at Thikkodi (Jan 24) for CLT - CAN stretch. Foundation work almost reached TLY.
/news/post/165762
86 km stretch between SRR n CLT may be commissioned soon....
CLT CAN by March 2015
86 km stretch between SRR n CLT may be commissioned soon....
CLT CAN by March 2015
Major Hurdle is going to be complete, Work will resume shortly