Electrification updates of SRR-CLT Strekch:--
As of now, Overhead work is completed till Kallayi station @ Calicut.
Wiring is completed till almost Meenchantha, and 99% upto Feroke
As of now, Overhead work is completed till Kallayi station @ Calicut.
Wiring is completed till almost Meenchantha, and 99% upto Feroke
8 Public Posts - Thu Jan 16, 2014
From 25th of this month, there should be train regulation - to remove the bottleneck of ERS.
02 Km -- ERS-ERCMD .
And also work at Mulanthurutty (MNTT) - Piravom Road (PVRD) will complete and commission before 31st March,
As of now, work is going on fast pace, this is only work is carrying on now, rest, Harippad-Ambalappuzha, Palghat-Pollachi GC, Punalur-Edaman-Shengottah is already...
more...
02 Km -- ERS-ERCMD .
And also work at Mulanthurutty (MNTT) - Piravom Road (PVRD) will complete and commission before 31st March,
As of now, work is going on fast pace, this is only work is carrying on now, rest, Harippad-Ambalappuzha, Palghat-Pollachi GC, Punalur-Edaman-Shengottah is already...
more...
4 Public Posts - Thu Jan 16, 2014
11 Public Posts - Fri Jan 17, 2014
1 Public Posts - Sat Jan 18, 2014
2 Public Posts - Mon Jan 20, 2014
1 Public Posts - Tue Jan 21, 2014
1 Public Posts - Mon Jan 27, 2014
1 Public Posts - Tue Jan 28, 2014
1 Public Posts - Thu Feb 13, 2014