Dec 30 2019 (14:13) 11302/Udyan Express (PT) | KWV/Kurduwadi Junction (4 PFs)
psanga_sur^~
psanga_sur^~ 5601 blog posts#PuneSolapurGulbargaDoubling #ElectrificationUpdates
Doubling of Bhigwan - Bhalawani section is progressing very slowly. But the electrification work is progressing at rapid speed. From Bhigwan to Madha we can see poles installed. Also wiring work started from Kurduwadi outer towards Bhigwan side. Wiring work is completed between Kurduwadi outer to Kem outer including Dhavlas Station. Kem & Bhalawani stations will be the next target for this month. By Dec 2020 Bhigwan - Kurduwadi - Miraj section will be electrified. In the last image, you can see construction of Daund Electric Loco Shed.
Doubling of Bhigwan - Bhalawani section is progressing very slowly. But the electrification work is progressing at rapid speed. From Bhigwan to Madha we can see poles installed. Also wiring work started from Kurduwadi outer towards Bhigwan side. Wiring work is completed between Kurduwadi outer to Kem outer including Dhavlas Station. Kem & Bhalawani stations will be the next target for this month. By Dec 2020 Bhigwan - Kurduwadi - Miraj section will be electrified. In the last image, you can see construction of Daund Electric Loco Shed.
3 Public Posts - Mon Dec 30, 2019
1 Public Posts - Fri Jan 17, 2020
1 Public Posts - Tue Jan 28, 2020
2 Public Posts - Thu Mar 19, 2020
1 Public Posts - Sun Mar 29, 2020
1 Public Posts - Thu Apr 02, 2020
1 Public Posts - Tue Jun 30, 2020
Electrification Updates of STA-MKP Section. Here are some Pictures of Current Work Progress of Electrification. #Electrificationupdates #STAMKPElectrification #ETALDElectrification
Electrification Work Updates from MKP End. See images. #STAMKPElectrification #ElectrificationUpdates
3 Public Posts - Wed Mar 06, 2019
1 Public Posts - Fri Mar 08, 2019
2 Public Posts - Mon Mar 11, 2019
Jul 30 2017 (12:16) GR/Kalaburagi Junction (Gulbarga) (4 PFs)
SunilKulkarni~
SunilKulkarni~ 2006 blog postsCatenary laying works in full swing GR station. The half way stopped electrification works have been restarted again. Already wadi till gulbarga outer all wiring is done now they are doing electrification of gulbarga station yard..
#ElectrificationUpdates
#ElectrificationUpdates
2 Public Posts - Sun Jul 30, 2017
1 Public Posts - Thu Aug 03, 2017
4 Public Posts - Sat Aug 26, 2017
3 Public Posts - Sun Aug 27, 2017
1 Public Posts - Mon Aug 28, 2017
4 Public Posts - Tue Aug 29, 2017
1 Public Posts - Wed Aug 30, 2017
1 Public Posts - Tue Sep 05, 2017
2 Public Posts - Thu Sep 07, 2017
1 Public Posts - Mon Sep 11, 2017
1 Public Posts - Sat Sep 23, 2017