#PuneSolapurGulbargaDoubling
CRS with speed trial at 120 Kmph is successfully completed between Bhigwan and Washimbe. Now Mumbai to Chennai line is FEDL.
22159 Mumbai - Chennai Superfast Express was the first train to run on new tracks at 12 midnight.
...
more...
CRS with speed trial at 120 Kmph is successfully completed between Bhigwan and Washimbe. Now Mumbai to Chennai line is FEDL.
22159 Mumbai - Chennai Superfast Express was the first train to run on new tracks at 12 midnight.
...
more...
3 Public Posts - Wed Aug 10, 2022
Aug 09 2022 (10:10) 22157/Mumbai CSMT - Chennai Egmore SF Mail (PT) | BGVN/Bhigwan (2 PFs)
psanga_sur^~
psanga_sur^~ 5601 blog posts#PuneSolapurGulbargaDoubling
Waiting for today's CRS of final stretch of long pending doubling project. After today's Bhigwan to Washimbe CRS entire Mumbai to Chennai line will be FEDL.
Above hastag will give...
more...
Waiting for today's CRS of final stretch of long pending doubling project. After today's Bhigwan to Washimbe CRS entire Mumbai to Chennai line will be FEDL.
Above hastag will give...
more...
11 Public Posts - Tue Aug 09, 2022
9 Public Posts - Wed Aug 10, 2022
1 Public Posts - Fri Aug 12, 2022
1 Public Posts - Mon Aug 15, 2022
#PuneSolapurGulbargaDoubling #Electrification
Mohol to Solapur Electrification CRS Speed Trial completed successfully.
Please check video for more details.
Uploading...
more...
Mohol to Solapur Electrification CRS Speed Trial completed successfully.
Please check video for more details.
Uploading...
more...
4 Public Posts - Fri Mar 25, 2022
Feb 24 2022 (11:30) 12158/Hutatma Express | PRWD/Parewadi (2 PFs)
psanga_sur^~
psanga_sur^~ 5601 blog postsFeb 19 2022 (04:23) 12158/Hutatma Express | BGVN/Bhigwan (2 PFs)
psanga_sur^~
psanga_sur^~ 5601 blog posts#PuneSolapurGulbargaDoubling
Washimbe to Parewadi - 90% work completed
Parewadi to Jinti Road - 90% work completed
Jinti Road to Bhigwan - 70% completed (track laying is in progress).
Expected...
more...
Washimbe to Parewadi - 90% work completed
Parewadi to Jinti Road - 90% work completed
Jinti Road to Bhigwan - 70% completed (track laying is in progress).
Expected...
more...