Nira-Lonand 7.64 km section doubling- Completed... more...
& commissioned for traffic today 22/10/23 with successful speed trial of 117 kmph and inspection of new track & track safe certification by CRS (Commissioner of Railway Safety) Shri. Manoj Arora and Chief Administrative Officer (construction) Shri Vivek Kumar Gupta.
CR has completed 137.67 km multitracking (doubling/3rd/4th line/new line) in current FY from April'23 to till date 2023
➡️Total Length-279.05 km ➡️Completed doubling- 174.85 km (62.65%) ➡️Total Cost- 4882.53 Crs ➡️Expenditure till date- 3200 Crs (65.53%) ➡️Overall physical progress- 86% ➡️Land Acquisition completed- 97.04 Hectare/115 Hectare (84.38%).
🟢Completed sections- 174.78 km (62.65%) Pune-Shindawane Ambale-Adarki Palsi-Jarandeshwar Satara-Koregaon Sangli-Shenoli
🟡Near completion sections- (Likely in this Fin.Year)- 73.70 km (26.41%) Palsi-Adarki Satara-Jarandeshwar Shenoli-Targaon Sangli-Miraj
🟠In progress- 30.50 km (10.86%)- Ambale-Shindawane Targaon-Koregaon
#Admin #Moderator Source Drm Pune X Handle
#CRInfraUpdates
🛤️Pune-Miraj Doubling Project:
✔️Total kms already commissioned: 167 km
🏗️In Progress: Pre-NI work for Commissioning of doubling of Nira-Lonand section of 7.64 km
▶️Set to be opened for passenger traffic shortly after clearance from CRS.
@Central_Railway
6 wishes शुभ यात्रा मेघश्याम भाई ।
सदा आप खुश रहना। உங்கள் பயணம் இனிதே அமைய வாழ்த்துக்கள் शुभ यात्रा Happy Journey మీ ప్రయాణం ఆహ్లాదకరంగా సాగాలని కోరుకుంటున్నాను ನಿಮ್ಮ ಪ್ರಯಾಣ ಸುಖಕರವಾಗಿರಲಿ
🥳🥳🥳
Onboard In
22497 - SGNR TPJ Humsafar Express
From
BKN - Bikaner Jn.
To
KJM - Krishnarajapuram
Or
SA - Salem Jn.
🥳🥳🥳
Important Note:This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks. Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.