For RailFans, seeing RAC-1/2/3 in Mumbai-UP Trains is more exciting than Election Results - rdb

Search Forum
<<prev entry    next entry>>
Blog Entry# 1034989
Posted: Mar 24 2014 (19:56)

47 Responses
Last Response: Apr 04 2014 (13:20)
1 Followers
General Travel
9278 views
4

Mar 24 2014 (19:56)   16566/Mangaluru Central - Yesvantpur Weekly Express
 
guest   1416 blog posts
Entry# 1034989            Tags  
Onboard in 16566.. Horrible... S2 to S5 is empty... In S1 and S7 have some people... In 2AC only 2 passengers.. In 3AC have little more passengers... All general coaches are occupied.. But no rush...
Flop train
Translate to English
Translate to Hindi

42 Posts

2833 views
0

Mar 25 2014 (23:21)
Venk   523 blog posts
Re# 1034989-43              
Let them make it public . Let ppl know whats the original agreement? For how many years? Or the usual 99 years govt rule. That way even pune cstm was a very challenging route. Look at the number of passengers. Even hassan majn route is developed similarly , with doubling n electrification , these restrictions may be removed.
Let's look at solutions till such dream projects might come true.
1. Let hmrda run trains for x years . No hard n fast rule that only swr or sr or irshud operate. Konkan railways
...
more...
is doing wonderful service in the coast.
Let hmrda introduce three more daily trains , with high priority between has sbc.
2, faster doubling of sbc ask.
3. Let sbc has route be taken on priority basis.
4. Till then run trains with aggressive tt upto hassan either via ask or mys.
5. Let hmrda be allowed to establish dedicated freight corridor from majn to mas via sbc , majn to vskp via ubl or bay.
6. All in all utilise the track, strengthen it. Plan freight trains accordingly. Doubling plus electrification is the best alternative.

Translate to English
Translate to Hindi

2786 views
1

Mar 25 2014 (23:21)
Minti^~
Minti^~   3450 blog posts
Re# 1034989-44              
the whole issue is regarding the objection by CRS after conversion from MG to BG. CRS has instructed to build catch sidings at all crossing stations in ghat between SBHR-SKLR. Until these are made available two passengers trains cannot be in this section at the same time. During day freight and passengers trains are allowed to cross one other but during night crossing is not allowed in this ghat section. To build catch sidings railway will have to acquire land, basically forest land and have to take permission from various ministries which looks tough. specially getting environmental clearance. In its latest request SWR has taken CLR-QLM reference where in similar terrain trains are running without restriction. Will have to wait for safety commissions reply.
Translate to English
Translate to Hindi

2727 views
0

Mar 25 2014 (23:50)
MCPNBR~
MCPNBR~   4911 blog posts
Re# 1034989-45              
I think restriction mainly between HAS - SBHR - MAQ. There is no much trains between HAS-SBC too.
Translate to English
Translate to Hindi

2630 views
0

Mar 25 2014 (23:53)
Minti^~
Minti^~   3450 blog posts
Re# 1034989-46              
restriction only in ghat between SBHR-SKLR. all other sections no restrictions.
Translate to English
Translate to Hindi

4470 views
0

Apr 04 2014 (13:20)
Umesh   65 blog posts
Re# 1034989-47              
Miraj Hubli Managalore has no train after conversion to BG.
Miraj to Trivandrum via Madgaon also there is no train.
Similarly no train between Vasco and Howrah or Guwahati after conversion of Miraj Latur to BG.
Also no connectivity between Goa and Bhuvaneswar after conversion of Miraj Kurduwadi.
Crores
...
more...
of money spent on conversion of Miraj Bangalore and Miraj Kurduwadi routes have gone as wastage. There is BG track but no useful trains.

Translate to English
Translate to Hindi
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy