Blog Entry# 1788327
Posted: Apr 02 2016 (20:16)

18 Responses
Last Response: Apr 03 2016 (18:14)
Rail News
9003 views
2

Other News
ML/Mumbai Local
Apr 02 2016 (20:06)   Mumbai: Railways lose Rs 14,000 for each suburban service
 

Jayashree^   51439 news posts
Entry# 1788327   News Entry# 263237         Tags   Past Edits
In 2014-15, the annual revenue from each 12-car train service was Rs 59.42 lakh, but the expenditure on it was a whopping Rs 111.08 lakh, causing...

8 Public Posts - Sat Apr 02, 2016

6 Public Posts - Sun Apr 03, 2016

4292 views
0

Apr 03 2016 (11:33)
S_V_Iyer^~
S_V_Iyer^~   18239 blog posts
Re# 1788327-15              
Now the Part 2 the projects that will relive me from the above situation and by which I will feel that I will turn back home alive:- (Counting from last couple to decades to present)

1. Borivali Virar Quadrapling and Virar Dahanu Road EMU services - It took them a decade for this project and Dahanu Road got connected to Suburban system just a year ago. By that time the commuters has multiplied 10x times and the services just 2x times.
...
more...

2. Thane Kurla 5th 6th line also took 15 years as against max 5 yrs proposed for completion.

3. I travel in Harbour line And I pity my co passengers. The creaky rakes and almost all of the fleet are twice as old as me are running in the corridor. I doubt that the floor will bear the weight of crowd till we reach the destination

4. The Siemens and Bombardier rakes inducted to reduce the passenger density have been inducted after a decade of their proposal and so as said above passengers have multiplied by 10 times during this period. AC rakes proposed to be inducted in 2011 have just rolled off ICF and trials and clearances awaits.

5. The only increase in Graph is the death tolls mounting every other day.

6. Commuters can't be blamed bcoz if they await an empty EMU (comfortable enuf to stand) they will probably reach their office by late noon and by that time its already time to pack up back home....

7. Atleast a dozen more projects have been sanctioned in various phases of MUTP and all are running behind by atleast 15 years and by the time of their completion the benefits will be in negative due to cost increase.

Now is it justified to always point fare increase for the retardedness of the officials who couldn't put projects on track on time which resulted in cost doubling?

Is it justified that pointing that Mumbai Suburban system is in losses bcoz the funds were not allocated by RB on time ?

Why should a passenger pay increased fare for no benefits or partial benefits?

Will you as a consumer purchase an apple for Rs. 20 which is half rotten ?

Translate to English
Translate to Hindi

3 Public Posts - Sun Apr 03, 2016
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy