Apr 26 2017 (14:27) SUBL/Hubballi South (Hubli) (1 PFs)
SingleTraveller^~
SingleTraveller^~ 3252 blog postsIn this post I will update the progress of doubling of Hubballi-Chikjajur and Arsikere-Tumakuru sections.
-
In this first post are pics from Hubballi South to Savanur stations and also of doubling progress. The pics are in the order from SUBL to SVNR.......
- Land levelling has been done at many places, is on at some places.
-...
more...
-
In this first post are pics from Hubballi South to Savanur stations and also of doubling progress. The pics are in the order from SUBL to SVNR.......
- Land levelling has been done at many places, is on at some places.
-...
more...
3 Public Posts - Wed Apr 26, 2017
Arsikere-Tumakuru.
-
Here is the best part. The work on this section (most needed to reduce congestion) is going on at a fast pace. Between ASK and TTR tracks have been laid at many places and other work along the section like bridge construction is on at night too. Since it was dark, not many pics could be taken. At TK, 4th PF is completed.
-
Here is the best part. The work on this section (most needed to reduce congestion) is going on at a fast pace. Between ASK and TTR tracks have been laid at many places and other work along the section like bridge construction is on at night too. Since it was dark, not many pics could be taken. At TK, 4th PF is completed.
1 Public Posts - Fri Apr 28, 2017
1 Public Posts - Sun Apr 30, 2017