Once upon a time, there was a great king called Vikramaditya - the WAM-4 - Shashank

Search Forum
<<prev entry    next entry>>
Blog Entry# 4015589
Posted: Nov 17 2018 (19:28)

73 Responses
Last Response: Nov 19 2018 (15:54)
Rail Fanning
32272 views
35

★★★
Nov 17 2018 (19:28)   BAY/Ballari Junction (Bellary) (4 PFs)
SteelCityRF^~
SteelCityRF^~   27572 blog posts
Entry# 4015589            Tags   Past Edits
Rail fanning at #BallariJnouter (towards Guntakal side) on #November15th2018
🔸 #Electrificationupdate of RUB 266A (locally known as Durgamma temple bridge) and ROB 267B (locally known as Satya Narayana Pet bridge) section from 208.9 km to 209.8 km (towards Guntakal side)
1) RUB 266A
2) 1st line towards left is up line. 2nd line towards right is down line
⏺️Adjacent
...
more...
up line
3) Pit for OHE pole / relay cabinet
4) Foundation for OHE pole
5) Foundation for relay cabinet
6) to 8) Foundations for OHE pole
⏺️Adjacent down line
9) Foundation for relay cabinet
10) to 12) Foundations for OHE pole
13) Foundations for relay cabinet
⏺️OHE poles adjacent both up & down lines
14) to 16) OHE poles (not aligned) were spotted after 209.0 km
17) Aligning of OHE poles under progress at 209.7 km
18) & 19) Aligned OHE poles were spotted after 209.7 km
🔸Update regarding ROB 267B (locally known as Satya Narayana Pet bridge) - #SNPetROB
⏺️Towards Gandhi Nagar / Nehru Colony
20) to 22) Construction of pillars completed. Girders placed on pillars for entire stretch
⏺️Towards Satya Narayana Pet (S N Pet)
23) to 26) Construction of pillars completed. Girders placed on pillars for entire stretch
27) & 28) Road construction under progress
Pictures source: Self

Translate to English
Translate to Hindi

23 Public Posts - Sat Nov 17, 2018

7 Public Posts - Sun Nov 18, 2018

21 Public Posts - Mon Nov 19, 2018

280 views
1

Nov 19 2018 (10:49)
Irshad13~
Irshad13~   8101 blog posts
Re# 4015589-57              
When SBC-UBL can start without RE at UBL so in same sense GDG-HG RE might starts from GDG side or they might start for already doubled sections because SWR will do its works under its area from HG outer to GDG and we already have 42.5km doubled from lachyan to Minchinal and now upto march-2019 71km will be doubled making 113.5km doubled from lachyan to Wandal so where they can start OHE pole digging process and OHE pole installations but everything is in NTPC hand if it pressurises IR then cant say GDG-HG might be the one get RE before SBC-UBL stretch.
Translate to English
Translate to Hindi

21 Public Posts - Mon Nov 19, 2018
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy