Kulali - Savalgi doubling update as on Oct 6, 2020 from RVNL CPM Mumbai :
Apparently there was an issue with a bridge in this section due to some local agitation. This issue has been resolved. Commissioning tolerances for the track is being achieved. Struggling with manpower shortages. Commissioning in Oct / Nov still appears in reach. Dates not confirmed yet.
This...
more...
Apparently there was an issue with a bridge in this section due to some local agitation. This issue has been resolved. Commissioning tolerances for the track is being achieved. Struggling with manpower shortages. Commissioning in Oct / Nov still appears in reach. Dates not confirmed yet.